Due to ongoing upgrade works on the Kasoa and Pokuase substations, there will be an erratic power supply in May, the Minister of Energy, Dr. Matthew Opoku Prempeh, has disclosed.
“Just two days ago, I received a letter from MiDA [Millennium Development Authority], who are helping upgrade the Pokuase and Kasoa substations.
“They informed me that the progress of the substation is such that in the month of May, there will be systematic power outages, so, we have invited both ECG and GRIDCo and in the light of that, let us sit and plan and communicate with the people who will be affected way before it happens”, he said.
Dr Prempeh made this known at a forum in Accra on Thursday, 8 April 2021.
He said his ministry’s current talks with the Ghana Grid Company Limited and the Electricity Company of Ghana, will help in strategising to minimise the impact of the outages on Ghanaians.
Also, he said “a revised energy policy is going through its final processes of consultation”.
“At the appropriate time of approval, it will be made available to everyone,” Dr Prempeh further noted.
The minister recently appealed to Ghanaians to have patience with the government as his ministry does all it can to solve the intermittent power outages currently afflicting the country.
Dr Prempeh went on a tour of some ongoing system upgrade projects of state power transmitter Ghana Grid Company Limited in the national capital, Accra on Tuesday, 6 April 2021.
Speaking to journalists during the tour, he said the intermittent power cuts are a result of system challenges and, thus, cannot be likened to the four-year power outages experienced under former President John Mahama from 2012 to 2016 due to production and financial problems, which necessitated a load-shedding timetable for the whole country.
“I think the issue of financial challenges doesn’t even come in here because they are doing the project, we can all see it, so, where does finance come in? The people don’t have money to buy lunch, or?” he wondered.
“I don’t know but as far as we can see, the project is an ongoing project, so, it’s not about finances, it’s just that if you’re renovating your house, sometimes, it’s more complicated and it’s more expensive than even building a new house”, he explained.
According to him, “these the lines that we’ve just been informed were strung, some in 1950, some from 1965, the power they were supposed to transmit, Accra has expanded tremendously, so, they are giving us lines that can improve the power situation in Accra”.
NPP Communicator Blames Mahama in Interview Over Viral Video Controversy
NPP Unveils Nationwide Reorganisation Timetable Ahead of 2026 Internal Elections
MPs Demand Tougher Action as Human Trafficking Cases Rise in Ghana
Abu Jinapor Demands Urgent Reforms to Address Ghana’s Cocoa Sector Challenges
Felix Kwakye Ofosu Defends Mahama Over Cocoa Pricing Remarks, Slams NPP Criticism
Asiedu Nketia Uses NDC Thank You Tour to Collect Feedback on Government
Speaker Urges Executive to Grant Parliament Permanent Land
Finance Expert Warns Cocoa Reforms Could Worsen COCOBOD Debt
Jinapor Swears In New VRA Resettlement Trust Fund Board