The Electricity Company of Ghana (ECG) has released a new load shedding timetable to take effect on Monday, June 28 and end on July 19.
The ‘dumsor’ will occur between the hours of 6 pm and 12midnight each day.
In a statement, the ECG said the planned outage is to enable the completion of construction works by the Ghana Grid Company (GRIDCo) on some bulk supply points and transmission cables in Accra.
“The load to the Trasacco Bulk Supply Point (BSP) will be managed to enable the construction of towers at the Volta, Accra East and Achimota substations and to complete the stringing and commissioning of a new double-circuit 161KV Volta-Achimota transmission line.”


NPP Communicator Blames Mahama in Interview Over Viral Video Controversy
NPP Unveils Nationwide Reorganisation Timetable Ahead of 2026 Internal Elections
MPs Demand Tougher Action as Human Trafficking Cases Rise in Ghana
Abu Jinapor Demands Urgent Reforms to Address Ghana’s Cocoa Sector Challenges
Felix Kwakye Ofosu Defends Mahama Over Cocoa Pricing Remarks, Slams NPP Criticism
Asiedu Nketia Uses NDC Thank You Tour to Collect Feedback on Government
Speaker Urges Executive to Grant Parliament Permanent Land
Finance Expert Warns Cocoa Reforms Could Worsen COCOBOD Debt
Jinapor Swears In New VRA Resettlement Trust Fund Board