The Electricity Company of Ghana (ECG) has released a new load shedding timetable to take effect on Monday, June 28 and end on July 19.
The ‘dumsor’ will occur between the hours of 6 pm and 12midnight each day.
In a statement, the ECG said the planned outage is to enable the completion of construction works by the Ghana Grid Company (GRIDCo) on some bulk supply points and transmission cables in Accra.
“The load to the Trasacco Bulk Supply Point (BSP) will be managed to enable the construction of towers at the Volta, Accra East and Achimota substations and to complete the stringing and commissioning of a new double-circuit 161KV Volta-Achimota transmission line.”
Former GIHOC MD Maxwell Kofi Jumah arrested by National Security operatives
“The Essence of Ghana” Book Launch
Ghana Reaffirms Solidarity with Niger and Sahel States, Endorses Regional Rebuilding Efforts
Bagbin Urges Niger to Embrace Ghana’s Constitutional Review Model for Democratic Rebuilding
Black Queens Arrive in Morocco Ahead of 2024 WAFCON Group Stage Battles
Africa Development Council Calls for Inclusion of Traditional Faiths in Ghana’s National Day of Prayer
Private Solomon Teye-Tsu Honoured for Rejecting Bribe from Illegal Miners at Bibiani Gold Mine
One Dead, Several Injured in VIP Bus and Toyota Venza Collision on Accra-Kumasi Highway
Bank of Ghana Reaffirms Support for PAPSS to Boost Cross-Border Trade and Digital Payments